Quaker Hill Phases | Anticipated Start Date | Anticipated Completion Date |
---|---|---|
Phase 1 (Complete) | ||
Phase 2 (Complete--please see note below) | ||
Phase 3-4 | March 2024* | October 2024* |
*Weather permitting. |
Phase 2 Property Restoration-- While most restoration work has been completed; any outstanding restoration will be completed once the weather permits. Thank you for your cooperation and support throughout the duration of this project.
NT Power will be retaining a third-party contractor to perform Phase 2-4 work with a planned construction start in September 2023 and proposed completion by Q3 of 2024, weather permitting.
There will be brief intermittent power interruptions required to complete this work for which you will be notified in advance. If for any reason extended outages are required, extended notification lead time will be given. NT Power will make every effort to reduce the frequency and duration of outages in completing this work.
Upon completion of the work any property or road restoration that is necessary will be completed to “as good or better” condition.
What To Expect
We apologize for any inconvenience this may cause and thank you in advance for your patience and support.
If you have any questions, or for more information, please reach out to our operations department using the form below.