Alert
Unfortunately, we are not able to proceed with your registration if you do not have the power to enter your company into a legally binding agreement with NT Power.
Load displacement is generation behind the meter. In other words, generation for the purposes of reducing your electricity consumption or demand. It can be a renewable or non-renewable energy source. The latest Load Displacement rules can be found on the Ontario Energy Board (OEB) website.
DER Classification | Rating |
---|---|
Micro |
≤ 10 kW
|
Small | (a) ≤ 500 kW connected on distribution system voltage < 15 kV (b) ≤ 1 MW connected on distribution system voltage ≥ 15 kV |
Mid-Sized | (a) ≤10 MW but > 500 kW connected on distribution system voltage < 15 kV (b) > 1 MW but ≤ 10 MW connected on distribution system voltage ≥ 15 kV |
Large |
> 10 MW
|
If you have any questions regarding the load displacement, please contact Newmarket-Tay Power's Generation Team Email: Click here to show mail address
The restricted feeders listed apply regardless of the program and regardless of the DER energy source type.
Stations – Armitage TS, Holland TS, Waubaushene TS
Restricted Feeders: none, please contact DER Team (Click here to show mail address) for more details.
This list will be updated at least every three months.
Other sources:
Application Process
1. Preliminary Information Request
2. Connection Application Request
3. Application Review and Offer to Connect
4. The Decision to Proceed and Install
5. Authorization to Connect
NOTE: Applicants are free to terminate the connection process during any stages, however, notification of termination is to be submitted to NT Power at Click here to show mail address
Application Process
1. Preliminary Information Request
2. Connection Impact Assessment (CIA) Application
3. Application Completeness Screening Process & Statement of Work
4. Connection Impact Assessment & Connection Cost Agreement
5. Design and Build
6. Commissioning and Verification
7. Connection Agreement
8. Authorization to Connect
NOTE: Applicants are free to terminate the connection process during any stages, however, notification of termination is to be submitted to NT Power at Click here to show mail address
Medium and Large-sized generation facilities typically involve business or industrial establishments. These systems usually involve complex technical and financial issues and should only be considered if the client has considerable generation experience.
Application Process
1. Preliminary Information Request
2. Connection Impact Assessment (CIA) Application
3. Application Completeness Screening Process & Statement of Work
4. Connection Impact Assessment & Connection Cost Agreement
5. Design and Build
6. Commissioning and Verification
7. Connection Agreement
8. Authorization to Connect
NOTE: Applicants are free to terminate the connection process during any stages, however, notification of termination is to be submitted to NT Power at Click here to show mail address
How long does the process take?
The process is dependent on size for small and medium sized projects it may take anywhere from 3 to 6 months.
How much does the process cost?
Prices can vary depending on project scope please submit an application for pricing.
Am I eligible for Generation?
Please make an application to determine eligibility.
How many credits do I have?
Please refer to your monthly hydro bill as it will indicate you current credit balance.
How much does a generation system cost?
Please contact a renewable generation installation company for costs.